1. The parameter(s) which determines which specific data will appear in the Material Master is/are |
(a) plant |
(b) company code |
(c) material type |
(d) industry sector |
2. Which department can enter data in Material Master is determined by |
(a) department |
(b) plant |
(c) material type |
(d) storage location |
3. The level at which classification view in Material Master is defined at |
(a) storage location |
(b) valuation type |
(c) plant & client |
(d) client |
4. The alternate unit of measure is defined in Material Master in |
(a) Basic data 1 view |
(b) Additional data screen |
(c) Storage view |
(d) MRP view |
5. With backflushing |
(a) we can post goods issue for the for the components of a Production order |
(b) we can post a goods receipt for the by-product |
(c) we can create a Material Master |
(d) all the above are true |
6. The characteristics of materials is defined in Material Master in |
(a) MRP1 view |
(b) Work Scheduling view |
(c) Classification view |
(d) None of the above |
7. Production Scheduler is maintained in Material Master in |
(a) Production view |
(b) Storage view |
(c) Work Scheduling view |
(d) MRP view |
8. If a material has to be backflushed only in specific Work Centre, then the data has to be maintained in |
(a) Material Master |
(b) Routing |
(c) BOM |
(d) Work Centre |
9. What is the field length of material number in Material Master? |
(a) 40 |
(b) 18 |
(c) 12 |
(d) 16 |
10. BOM is called recursive when |
(a) the BOM contains two identical components |
(b) the base quantity is unit |
(c) the components are non-stock item |
(d) the component and header item are same |